Back to projects

Sewer improvements on Gerard Street, and improvements to the aeration system of Renaud lagoon

Saint-Antoine, New Brunswick

completeWastewaterSCF
Federal contribution
$699,953
Federal share33%

of $2.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 22, 2015
2016201720182019
Built

Approved 2 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Village of Saint-Antoine
Construction start
Sep 28, 2015(actual)
Construction end
Oct 2, 2019(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Sep 8, 2015
  • Construction end10 months lateforecast Nov 30, 2018

Also in Saint-Antoine

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46075 in the federal list. How to read these figures.