Upgrade of Saint-Antoine Wastewater Treatment Facility

Saint-Antoine, New Brunswick

completeWastewaterCC
Federal contribution
$1.1M
$1,111,925
Federal share33%

of $3.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2009
201020112012
Built

Approved 7 weeks before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
Village of Saint-Antoine
Construction start
Jun 9, 2010(actual)
Construction end
Dec 8, 2011(actual)

Against the original forecast

  • Construction start8 months lateforecast Oct 1, 2009
  • Construction end3 weeks earlyforecast Dec 31, 2011