Wehwehneh Bahgahkinahgohn It Is Visible Southern Chiefs' Organization Hudson's Bay Proposal - Downtown Winnipeg

Winnipeg, Manitoba

approvedOtherGICB
Federal contribution
$25.0M
$25,000,000
Federal share40%

of $61.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2024
today
2024202520262027
BuiltForecast

Approved 4 months before the announcement.

Program
Green and Inclusive Community Buildings Program
Construction start
Jul 17, 2023(forecast)
Construction end
Mar 31, 2027(forecast)