Back to projects

Sydney Street Courthouse Theatre

Saint John, New Brunswick

underwayCultureGICB
Federal contribution
$12.0M
$12,000,000
Federal share44%

of $27.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 29, 2024
today
20202022202420262028
BuiltForecast

Approved 9 months before the announcement.

Program
Green and Inclusive Community Buildings Program
Ultimate recipient
Saint John Theatre Company
Construction start
Mar 1, 2020(actual)
Construction end
Aug 17, 2028(forecast)

Against the original forecast

  • Construction start4.3 years earlyforecast Jun 3, 2024

Also in Saint John