The New MIFO: Construction of a Cultural and Recreational Community Centre
Federal contribution
$25.0M
$25,000,000
Federal share46%
of $54.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 2, 2024
today
2024202520262027
BuiltForecast
Approved 3 months before the announcement.
- Program
- Green and Inclusive Community Buildings Program
- Ultimate recipient
- Mouvement d'implication francophone d'Orléans (MIFO)
- Construction start
- Jul 7, 2025(actual)
- Construction end
- Jul 16, 2027(forecast)
Against the original forecast
- Construction start5 weeks lateforecast Jun 5, 2025