Haines Junction Infrastructure Upgrades – Phase 4

Haines Junction, Yukon

underwayDrinking WaterGIS
Federal contribution
$7.5M
$7,500,000
Federal share75%

of $10.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 4, 2024
today
202520262027
BuiltForecast

Approved 7 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Village of Haines Junction
Construction start
Jul 1, 2024(actual)
Construction end
Nov 30, 2026(forecast)

Against the original forecast

  • Construction start2 months lateforecast May 1, 2024