Haines Junction Infrastructure Upgrades - Phase 3
Federal contribution
$6.5M
$6,475,263
Federal share75%
of $8.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 4, 2021
202120222023
Built
Approved 16 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Village of Haines Junction
- Construction start
- Jun 8, 2021(actual)
- Construction end
- Nov 6, 2023(actual)
Against the original forecast
- Construction start5 weeks lateforecast May 1, 2021
- Construction end3 months earlyforecast Jan 26, 2024
Also in Haines Junction
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56580 in the federal list. How to read these figures.