Haines Junction Infrastructure Upgrades - Phase 3

Haines Junction, Yukon

completeWastewaterGIS
Federal contribution
$6.5M
$6,475,263
Federal share75%

of $8.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 4, 2021
202120222023
Built

Approved 16 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Village of Haines Junction
Construction start
Jun 8, 2021(actual)
Construction end
Nov 6, 2023(actual)

Against the original forecast

  • Construction start5 weeks lateforecast May 1, 2021
  • Construction end3 months earlyforecast Jan 26, 2024