Champagne and Aishihik First Nations' Cultural Centre

Haines Junction, Yukon

completeCultureMRIF
Federal contribution
$4.0M
$3,999,999
Federal share33%

of $12.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
2010201220142016
Built

Approved 6.7 years before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Aug 19, 2010(actual)
Construction end
Apr 22, 2013(actual)

Against the original forecast

  • Construction start3 years lateforecast Sep 1, 2007
  • Construction end2.1 years lateforecast Mar 31, 2011