Champagne and Aishihik First Nations' Cultural Centre
Federal contribution
$4.0M
$3,999,999
Federal share33%
of $12.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
2010201220142016
Built
Approved 6.7 years before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- First Nations of Champagne/Aishihik
- Construction start
- Aug 19, 2010(actual)
- Construction end
- Apr 22, 2013(actual)
Against the original forecast
- Construction start3 years lateforecast Sep 1, 2007
- Construction end2.1 years lateforecast Mar 31, 2011
Also in Haines Junction
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 18541 in the federal list. How to read these figures.