Purchases to support transit for Port Hawkesbury, Nova Scotia.

Port Hawkesbury, Nova Scotia

underwayPublic TransitRTSF
Federal contribution
$340,080
Federal share80%

of $425.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 26, 2025
today
20252026
BuiltForecast

Approved 4 months before the announcement.

Program
Permanent Public Transit Program
Construction start
Oct 28, 2024(actual)
Construction end
Sep 30, 2026(forecast)

Against the original forecast

  • Construction start8 months lateforecast Mar 1, 2024