Back to projects

Town of Port Hawkesbury Active Transportation

Port Hawkesbury, Nova Scotia

completeActive TransportationATF
Federal contribution
$296,259
Federal share60%

of $494.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 26, 2025
202320242025
Built

Approved 2.6 years before the announcement.

Program
Active Transportation Fund
Ultimate recipient
Town of Port Hawkesbury
Construction start
Nov 21, 2023(actual)
Construction end
Oct 25, 2024(actual)

Against the original forecast

  • Construction start18 months lateforecast May 31, 2022
  • Construction end24 months lateforecast Nov 3, 2022