Town of Port Hawkesbury Active Transportation
Federal contribution
$296,259
Federal share60%
of $494.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 26, 2025
202320242025
Built
Approved 2.6 years before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Town of Port Hawkesbury
- Construction start
- Nov 21, 2023(actual)
- Construction end
- Oct 25, 2024(actual)
Against the original forecast
- Construction start18 months lateforecast May 31, 2022
- Construction end24 months lateforecast Nov 3, 2022
Also in Port Hawkesbury