Street Upgrading

Port Hawkesbury, Nova Scotia

completeHighways and RoadsCC Top Up
Federal contribution
$204,663
Federal share33%

of $614.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 30, 2009
2010
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Town of Port Hawkesbury
Construction start
Oct 21, 2009(actual)
Construction end
Oct 13, 2010(actual)

Against the original forecast

  • Construction start5 months lateforecast Jun 1, 2009
  • Construction end9 months lateforecast Dec 31, 2009