Back to projects

Transit Needs Assessment for the Town of Gander, NL

Gander, Newfoundland and Labrador

underwayCapacity BuildingRTSF
Federal contribution
$50,000
Federal share83%

of $60.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 16, 2026
today
202520262027
BuiltForecast

Approved 16 months before the announcement.

Program
Permanent Public Transit Program
Ultimate recipient
Town of Gander
Construction start
Jan 15, 2025(actual)
Construction end
Jan 15, 2027(forecast)

Also in Gander

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 122336 in the federal list. How to read these figures.