New Multiplex and Soccer/Track and Field Facility
Gander, Newfoundland and Labrador
Federal contribution
$2.2M
$2,242,264
Federal share33%
of $6.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 16, 2020
20212022202320242025
Built
Approved 4 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Town of Gander
- Construction start
- Jun 7, 2021(actual)
- Construction end
- Feb 28, 2025(actual)
Against the original forecast
- Construction end3 months lateforecast Nov 30, 2024
Also in Gander
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57311 in the federal list. How to read these figures.