New Gander Wastewater Treatment Facility

Gander, Newfoundland and Labrador

completeWastewaterNRP
Federal contribution
$10.6M
$10,574,604
Federal share30%

of $35.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2017
2017201920212023
Built

Approved 8 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Ultimate recipient
Town of Gander
Construction start
Nov 8, 2017(actual)
Construction end
Dec 12, 2022(actual)

Against the original forecast

  • Construction start7 months lateforecast Apr 1, 2017