Water and Sewer and Street Improvements, Cooper Boulevard, Read Street, and Gilmore Street
Gander, Newfoundland and Labrador
Federal contribution
$529,346
Federal share33%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 20, 2016
20172018201920202021
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Gander
- Construction start
- Aug 18, 2017(actual)
- Construction end
- Aug 31, 2021(actual)
Against the original forecast
- Construction start7 months earlyforecast Apr 1, 2018
- Construction end4 weeks lateforecast Jul 31, 2021
Also in Gander
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46684 in the federal list. How to read these figures.