Back to projects

Water and Sewer and Street Improvements, Cooper Boulevard, Read Street, and Gilmore Street

Gander, Newfoundland and Labrador

completeDrinking WaterSCF
Federal contribution
$529,346
Federal share33%

of $1.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 20, 2016
20172018201920202021
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Gander
Construction start
Aug 18, 2017(actual)
Construction end
Aug 31, 2021(actual)

Against the original forecast

  • Construction start7 months earlyforecast Apr 1, 2018
  • Construction end4 weeks lateforecast Jul 31, 2021

Also in Gander