Thorne Avenue Lift Station

Saint John, New Brunswick

completeWastewaterMRIF
Federal contribution
$2.8M
$2,766,666
Federal share33%

of $8.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 24, 2006
20062008201020122014
Built

Approved 3 months after the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
City of Saint John
Construction start
Jul 6, 2006(actual)
Construction end
Mar 26, 2014(actual)

Against the original forecast

  • Construction start10 months lateforecast Sep 1, 2005
  • Construction end6.6 years lateforecast Aug 15, 2007

Also in Saint John

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12283 in the federal list. How to read these figures.