Transit Feasibility Study for the Town of Deer Lake, NL
Deer Lake, Newfoundland and Labrador
Federal contribution
$50,000
Federal share100%
of $50.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 16, 2026
20252026
BuiltForecast
Approved 11 months before the announcement.
- Program
- Permanent Public Transit Program
- Ultimate recipient
- Town of Deer Lake
- Construction start
- Apr 1, 2024(forecast)
- Construction end
- Oct 1, 2024(forecast)