Water System Improvements

Rivière-Verte, New Brunswick

completeDrinking WaterMRIF
Federal contribution
$594,120
Federal share33%

of $1.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 17, 2005
20062007200820092010
Built

Approved 8 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Village of Rivière-Verte
Construction start
Aug 23, 2005(actual)
Construction end
Nov 18, 2009(actual)

Against the original forecast

  • Construction start6 weeks earlyforecast Oct 1, 2005
  • Construction end6 months lateforecast May 31, 2009

Also in Rivière-Verte

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12352 in the federal list. How to read these figures.