completeHighways and RoadsISF
Federal contribution
$1.5M
$1,505,000
Federal share50%

of $3.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 12, 2009
ApprovedJul 28, 2010
2010
Built

Approved 14 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of New Brunswick
Construction start
Jul 13, 2009(actual)
Construction end
Aug 6, 2010(actual)

Against the original forecast

  • Construction start3 weeks earlyforecast Jul 31, 2009
  • Construction end8 weeks earlyforecast Sep 30, 2010