Madawaska Maliseet First Nation - Infrastructure Renovations Program (IRP)
Federal contribution
$289,703
Federal share75%
of $386.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 1, 2021
2021
Built
Approved 10 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Madawaska Maliseet First Nation
- Construction start
- Oct 5, 2020(actual)
- Construction end
- Nov 23, 2020(actual)
Also in Rivière-Verte