Force Main Sewer
Federal contribution
$634,090
Federal share33%
of $1.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 18, 2005
2006
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Village of Teslin
- Construction start
- Jun 2, 2005(actual)
- Construction end
- Apr 30, 2006(actual)
Against the original forecast
- Construction start4 weeks earlyforecast Jul 1, 2005
- Construction end7 months lateforecast Sep 30, 2005
Also in Teslin
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12359 in the federal list. How to read these figures.