RICC (Rothesay Intergenerational Community Complex)
Federal contribution
$7.0M
$7,000,000
Federal share57%
of $12.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 22, 2025
today
2026202720282029
BuiltForecast
- Program
- Green and Inclusive Community Buildings Program
- Ultimate recipient
- Rothesay
- Construction start
- Apr 26, 2027(forecast)
- Construction end
- Dec 31, 2028(forecast)
Also in Rothesay