Expansion of the Water System in West Rothesay

Rothesay, New Brunswick

completeDrinking WaterISF
Federal contribution
$1.3M
$1,270,000
Federal share33%

of $3.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 14, 2009
20102011
Built
Program
Infrastructure Stimulus Fund
Ultimate recipient
Town of Rothesay
Construction start
Jun 21, 2010(actual)
Construction end
Dec 31, 2010(actual)

Against the original forecast

  • Construction start5 weeks lateforecast May 15, 2010
  • Construction end4 weeks lateforecast Nov 30, 2010