Expansion of the Water System in West Rothesay
Federal contribution
$1.3M
$1,270,000
Federal share33%
of $3.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 14, 2009
20102011
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Town of Rothesay
- Construction start
- Jun 21, 2010(actual)
- Construction end
- Dec 31, 2010(actual)
Against the original forecast
- Construction start5 weeks lateforecast May 15, 2010
- Construction end4 weeks lateforecast Nov 30, 2010