Back to projects

Municipal Water System Expansion

Rothesay, New Brunswick

completeDrinking WaterCC Top Up
Federal contribution
$1.5M
$1,500,000
Federal share19%

of $7.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 14, 2009
20102011
Built

Approved 3 weeks before the announcement.

Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Town of Rothesay
Construction start
Jun 21, 2010(actual)
Construction end
Oct 15, 2011(actual)

Against the original forecast

  • Construction start7 weeks lateforecast May 1, 2010
  • Construction end2 weeks lateforecast Sep 30, 2011