Water System Improvements
Fredericton Junction, New Brunswick
Federal contribution
$177,033
Federal share33%
of $531.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
2009201120132015
Built
Approved 7.6 years before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Village of Fredericton Junction
- Construction start
- Aug 19, 2008(actual)
- Construction end
- Nov 1, 2010(actual)
Against the original forecast
- Construction end15 months lateforecast Jul 31, 2009
Also in Fredericton Junction
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12398 in the federal list. How to read these figures.