Construction of a Community Complex

Fredericton Junction, New Brunswick

completeRecreationMRIF
Federal contribution
$1.3M
$1,333,333
Federal share33%

of $4.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2007
2007200820092010
Built

Approved 7 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Tri-County Complex Inc.
Construction start
Jan 23, 2007(actual)
Construction end
Mar 23, 2010(actual)

Against the original forecast

  • Construction start8 months earlyforecast Oct 1, 2007
  • Construction end15 months lateforecast Dec 31, 2008

Also in Fredericton Junction

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14746 in the federal list. How to read these figures.