Construction of a Community Complex
Fredericton Junction, New Brunswick
Federal contribution
$1.3M
$1,333,333
Federal share33%
of $4.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2007
2007200820092010
Built
Approved 7 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Tri-County Complex Inc.
- Construction start
- Jan 23, 2007(actual)
- Construction end
- Mar 23, 2010(actual)
Against the original forecast
- Construction start8 months earlyforecast Oct 1, 2007
- Construction end15 months lateforecast Dec 31, 2008
Also in Fredericton Junction
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 14746 in the federal list. How to read these figures.