Back to projects

Wastewater Treatment Plant Upgrade

Fredericton Junction, New Brunswick

completeWastewaterMRIF
Federal contribution
$249,323
Federal share33%

of $748.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2007
2008
Built

Approved 7 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Jan 23, 2007(actual)
Construction end
Aug 6, 2008(actual)

Against the original forecast

  • Construction start2 months earlyforecast Apr 1, 2007
  • Construction end12 months lateforecast Jul 31, 2007

Also in Fredericton Junction

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 15815 in the federal list. How to read these figures.