Water Treatment Plant Upgrade
Federal contribution
$250,000
Federal share15%
of $1.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 27, 2006
2006
Built
Approved 5 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Meadow Lake
- Construction start
- Dec 1, 2005(actual)
- Construction end
- Sep 5, 2006(actual)
Against the original forecast
- Construction start4 weeks lateforecast Oct 31, 2005
- Construction end5 months lateforecast Mar 31, 2006
Also in Meadow Lake
- Meadow Lake Tribal Council Bioenergy$52.5M
- City of Meadow Lake - Recreation & Civic Centre$14.9M
- Sewage replacement and relocation for Meadow Lake sewage lagoon$8.0M
- Water Quality - Organic Removal Upgrades to Water Treatment Plant$1.6M
- SaskWater - Meadow Lake - Water Treatment Plant Actiflo Clarification$990.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12399 in the federal list. How to read these figures.