Water Treatment Plant Upgrade

Meadow Lake, Saskatchewan

completeDrinking WaterMRIF
Federal contribution
$250,000
Federal share15%

of $1.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 27, 2006
2006
Built

Approved 5 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Meadow Lake
Construction start
Dec 1, 2005(actual)
Construction end
Sep 5, 2006(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Oct 31, 2005
  • Construction end5 months lateforecast Mar 31, 2006