Back to projects

SaskWater - Meadow Lake - Water Treatment Plant Actiflo Clarification

Meadow Lake, Saskatchewan

completeDrinking WaterGIS
Federal contribution
$990,000
Federal share40%

of $2.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 23, 2021
202120222023
Built

Approved 6 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
SaskWater
Construction start
Jul 22, 2022(actual)
Construction end
Apr 6, 2023(actual)

Against the original forecast

  • Construction start3 months lateforecast May 2, 2022
  • Construction end2 months lateforecast Jan 24, 2023

Also in Meadow Lake

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57414 in the federal list. How to read these figures.