SaskWater - Meadow Lake - Water Treatment Plant Actiflo Clarification
Federal contribution
$990,000
Federal share40%
of $2.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 23, 2021
202120222023
Built
Approved 6 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- SaskWater
- Construction start
- Jul 22, 2022(actual)
- Construction end
- Apr 6, 2023(actual)
Against the original forecast
- Construction start3 months lateforecast May 2, 2022
- Construction end2 months lateforecast Jan 24, 2023
Also in Meadow Lake
- Meadow Lake Tribal Council Bioenergy$52.5M
- City of Meadow Lake - Recreation & Civic Centre$14.9M
- Sewage replacement and relocation for Meadow Lake sewage lagoon$8.0M
- Water Quality - Organic Removal Upgrades to Water Treatment Plant$1.6M
- Road Construction - Hot Mix Surfacing along a Muncipal Road in Meadow Lake$923.3K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57414 in the federal list. How to read these figures.