Schedule
Announced and approvedJul 31, 2015
2016201720182019
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- City of Meadow Lake
- Construction start
- Jul 17, 2017(actual)
- Construction end
- Feb 28, 2019(actual)
Against the original forecast
- Construction end4 weeks earlyforecast Mar 31, 2019
Also in Meadow Lake
- Meadow Lake Tribal Council Bioenergy$52.5M
- City of Meadow Lake - Recreation & Civic Centre$14.9M
- Sewage replacement and relocation for Meadow Lake sewage lagoon$8.0M
- SaskWater - Meadow Lake - Water Treatment Plant Actiflo Clarification$990.0K
- Road Construction - Hot Mix Surfacing along a Muncipal Road in Meadow Lake$923.3K