Road Construction - Hot Mix Surfacing along a Muncipal Road in Meadow Lake

Meadow Lake, Saskatchewan

completeHighways and RoadsISF
Federal contribution
$923,333
Federal share33%

of $2.8M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 29, 2009
ApprovedJan 27, 2010
2010
Built

Approved 7 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Saskatchewan
Construction start
Aug 25, 2009(actual)
Construction end
Oct 31, 2009(actual)

Against the original forecast

  • Construction end16 months earlyforecast Mar 1, 2011

Also in Meadow Lake

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 33457 in the federal list. How to read these figures.