Back to projects

Niverville Wastewater Treatment Upgrades

Niverville, Manitoba

completeWastewaterMRIF
Federal contribution
$800,000
Federal share27%

of $3.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 24, 2006
200620072008
Built

Approved 4 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Niverville
Construction start
Nov 24, 2005(actual)
Construction end
Mar 10, 2008(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Oct 1, 2005
  • Construction end17 months lateforecast Oct 1, 2006