Niverville Wastewater Treatment Upgrades
Federal contribution
$800,000
Federal share27%
of $3.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 24, 2006
200620072008
Built
Approved 4 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Niverville
- Construction start
- Nov 24, 2005(actual)
- Construction end
- Mar 10, 2008(actual)
Against the original forecast
- Construction start8 weeks lateforecast Oct 1, 2005
- Construction end17 months lateforecast Oct 1, 2006
Also in Niverville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12511 in the federal list. How to read these figures.