Niverville Community Resource Centre
Federal contribution
$7.7M
$7,717,121
Federal share40%
of $19.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 12, 2019
202020212022
Built
Approved 7 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Town of Niverville
- Construction start
- Jul 16, 2019(actual)
- Construction end
- Mar 23, 2022(actual)
Against the original forecast
- Construction start5 months lateforecast Mar 1, 2019
- Construction end5 months lateforecast Oct 31, 2021