2022 Active Transportation Renewals and Improvements in Niverville, Manitoba
Federal contribution
$24,000
Federal share60%
of $40.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 17, 2023
2023
Built
Approved 16 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Town of Niverville
- Construction start
- Jun 2, 2023(actual)
- Construction end
- Aug 1, 2023(actual)
Against the original forecast
- Construction start12 months lateforecast May 30, 2022
- Construction end3 months earlyforecast Nov 1, 2023
Also in Niverville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64126 in the federal list. How to read these figures.