Town of Watson Lake Pumphouse Rehabilitation & Well

Watson Lake, Yukon

completeDrinking WaterMRIF
Federal contribution
$250,283
Federal share25%

of $989.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 18, 2005
20062007
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Watson Lake
Construction start
May 1, 2006(actual)
Construction end
Mar 15, 2007(actual)

Against the original forecast

  • Construction start22 months lateforecast Jul 1, 2004
  • Construction end14 months lateforecast Dec 31, 2005

Also in Watson Lake

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12543 in the federal list. How to read these figures.