The Pas Sewage Lift Station Upgrades
Federal contribution
$196,000
Federal share27%
of $735.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 9, 2008
20082009201020112012
Built
Approved 7 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of The Pas
- Construction start
- Jan 16, 2008(actual)
- Construction end
- Apr 2, 2012(actual)
Against the original forecast
- Construction start19 months lateforecast Jun 30, 2006
- Construction end12 months lateforecast Mar 31, 2011
Also in The Pas
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12552 in the federal list. How to read these figures.