Back to projects

The Pas Sewage Lift Station Upgrades

The Pas, Manitoba

completeWastewaterMRIF
Federal contribution
$196,000
Federal share27%

of $735.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 9, 2008
20082009201020112012
Built

Approved 7 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of The Pas
Construction start
Jan 16, 2008(actual)
Construction end
Apr 2, 2012(actual)

Against the original forecast

  • Construction start19 months lateforecast Jun 30, 2006
  • Construction end12 months lateforecast Mar 31, 2011

Also in The Pas

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12552 in the federal list. How to read these figures.