Sam Waller Museum Exterior Building Repairs
Federal contribution
$11,079
Federal share35%
of $31.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 23, 2021
20212022
Built
Approved 7 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Sam Waller Museum Board
- Construction start
- Sep 22, 2021(actual)
- Construction end
- Oct 20, 2022(actual)
Against the original forecast
- Construction start4 months lateforecast Jun 1, 2021
Also in The Pas
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58252 in the federal list. How to read these figures.