The Pas - Handi-Van Purchase

The Pas, Manitoba

completePublic TransitPTIF
Federal contribution
$51,443
Federal share50%

of $102.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
Built

Approved 5 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
Town of The Pas
Construction start
Jun 22, 2017(actual)
Construction end
Nov 23, 2017(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 15, 2017
  • Construction end5 weeks earlyforecast Dec 31, 2017

Also in The Pas

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49268 in the federal list. How to read these figures.