Back to projects

Water Tank Replacement

Sainte-Anne-de-Madawaska, New Brunswick

completeDrinking WaterMRIF
Federal contribution
$243,415
Federal share33%

of $730.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 30, 2006
20072008
Built
Program
Municipal Rural Infrastructure Fund
Construction start
Mar 17, 2006(actual)
Construction end
Apr 7, 2008(actual)

Against the original forecast

  • Construction start6 weeks earlyforecast May 1, 2006
  • Construction end16 months lateforecast Dec 1, 2006

Also in Sainte-Anne-de-Madawaska

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12597 in the federal list. How to read these figures.