Improvement of drinking water quality
Sainte-Anne-de-Madawaska, New Brunswick
Federal contribution
$224,524
Federal share33%
of $673.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 6, 2009
20102011
Built
Approved 2 weeks before the announcement.
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Village of Sainte-Anne-De-Madawaska
- Construction start
- Sep 27, 2010(actual)
- Construction end
- Mar 31, 2011(actual)
Against the original forecast
- Construction start10 months lateforecast Dec 1, 2009
- Construction end6 months lateforecast Sep 30, 2010