Storm and sanitary sewer repairs, Lebel and Commercial Streets
Sainte-Anne-de-Madawaska, New Brunswick
Federal contribution
$192,838
Federal share41%
of $474.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 18, 2016
2017
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Village of Saint-François-de-Madawaska
- Construction start
- Jun 6, 2017(actual)
- Construction end
- Oct 11, 2017(actual)
Against the original forecast
- Construction start5 weeks lateforecast May 1, 2017
- Construction end12 months earlyforecast Sep 28, 2018
Also in Sainte-Anne-de-Madawaska
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47336 in the federal list. How to read these figures.