East Storm Drainage System
Federal contribution
$415,000
Federal share25%
of $1.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 16, 2005
2006200720082009
Built
Approved 7 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- City of Lloydminster
- Construction start
- Jul 31, 2005(actual)
- Construction end
- Dec 10, 2008(actual)
Against the original forecast
- Construction end4 months earlyforecast Mar 31, 2009
Also in Lloydminster
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12678 in the federal list. How to read these figures.