Greenstreet Road
Federal contribution
$378,809
Federal share33%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 20, 2009
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Rural Municipality of Britannia
- Construction start
- May 6, 2009(actual)
- Construction end
- Sep 16, 2009(actual)
Against the original forecast
- Construction end2.5 years earlyforecast Mar 31, 2012
Also in Lloydminster