Sewage Treatment Plant - Headworks Facility

Lloydminster, Saskatchewan

completeWastewaterCC
Federal contribution
$900,949
Federal share33%

of $2.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 29, 2009
20102011201220132014
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
City of Lloydminster
Construction start
Aug 16, 2010(actual)
Construction end
Oct 31, 2013(actual)

Against the original forecast

  • Construction start4 months lateforecast May 1, 2010