Water Reservoir Expansion
Federal contribution
$62,950
Federal share25%
of $251.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 27, 2006
20062007
Built
Approved 5 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Saltcoats
- Construction start
- Oct 31, 2005(actual)
- Construction end
- Jan 27, 2007(actual)
Against the original forecast
- Construction start5 months earlyforecast Apr 1, 2006
- Construction end2 months earlyforecast Mar 31, 2007
Also in Saltcoats
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12757 in the federal list. How to read these figures.