Town of Saltcoats - Saltcoats Landfill Corrective Action and Closure
Federal contribution
$48,397
Federal share40%
of $121.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2021
20212022202320242025
Built
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Saltcoats
- Construction start
- Apr 1, 2021(actual)
- Construction end
- Jun 30, 2025(actual)
Against the original forecast
- Construction end6 months lateforecast Dec 31, 2024
Also in Saltcoats
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57437 in the federal list. How to read these figures.