Back to projects

Grid Road Upgrade

Saltcoats, Saskatchewan

completeHighways and RoadsMRIF
Federal contribution
$61,558
Federal share25%

of $246.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 5, 2007
200720082009
Built

Approved 2 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Dec 20, 2006(actual)
Construction end
Jun 3, 2009(actual)

Against the original forecast

  • Construction end10 months earlyforecast Mar 31, 2010

Also in Saltcoats

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16735 in the federal list. How to read these figures.