Community Arena Complex

Fredericton, New Brunswick

completeRecreationMRIF
Federal contribution
$1.0M
$1,000,000
Federal share7%

of $14.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 22, 2006
2007
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
City of Fredericton
Construction start
Mar 17, 2006(actual)
Construction end
Mar 14, 2007(actual)

Against the original forecast

  • Construction start6 months lateforecast Sep 1, 2005
  • Construction end6 months lateforecast Sep 1, 2006

Also in Fredericton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12767 in the federal list. How to read these figures.