Fredericton - Core Water and Sewer Infrastructure Multi-Year Renewal

Fredericton, New Brunswick

underwayDrinking WaterGIS
Federal contribution
$12.6M
$12,641,264
Federal share40%

of $31.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 28, 2022
today
202320242025202620272028
BuiltForecast

Approved 7 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
City of Fredericton
Construction start
May 17, 2022(actual)
Construction end
Dec 31, 2027(forecast)