Back to projects

Multiple Natural and Structural Infrastructure Projects to Adapt to Pluvial and Fluvial Flood Events in Fredericton

Fredericton, New Brunswick

underwayDisaster MitigationDMAF
Federal contribution
$11.4M
$11,400,000
Federal share40%

of $28.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 15, 2019
today
20192022202520282031
BuiltForecast

Approved 7 weeks before the announcement.

Program
Disaster Mitigation and Adaptation Fund
Ultimate recipient
City of Fredericton
Construction start
Nov 15, 2019(actual)
Construction end
Dec 31, 2032(forecast)

Also in Fredericton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52817 in the federal list. How to read these figures.