Multiple Natural and Structural Infrastructure Projects to Adapt to Pluvial and Fluvial Flood Events in Fredericton
Federal contribution
$11.4M
$11,400,000
Federal share40%
of $28.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 15, 2019
today
20192022202520282031
BuiltForecast
Approved 7 weeks before the announcement.
- Program
- Disaster Mitigation and Adaptation Fund
- Ultimate recipient
- City of Fredericton
- Construction start
- Nov 15, 2019(actual)
- Construction end
- Dec 31, 2032(forecast)